Marston and Oriole Street Improvements
Marston and Oriole Street Improvements

7/17/12: Scott Dugas Trucking and Excavation plans on starting around the second week of August and completing the project by the end of the month, weather permitting.   Materials and equipment should be arriving on site in the next few weeks. 

7/3/12: The Town of Falmouth is ready to award the drainage system replacement project to Scott Dugas Trucking and Excavation of Yarmouth, Maine. They were the low bidder at $76,314.00. Work is anticipated to start around July 15, 2012. The contract completion date is October 1, 2012. Their scope of work will include approximately 860 lineal feet of storm drainage pipe, 11 catch basins, incidental paving work, rip-rap slope stabilization and other minor improvements. Thank you for your patience in advance!